đ Sprint 1: Pre-Production + Owen Day in the Life
Feb 2 â Feb 20 âĸ 18 days âĸ Owner: Owen
37
Total Tasks
0
Completed
37
Remaining
0%
Progress
đ Week 1: Feb 2 â Feb 9
Pre-Production â Scripts & Shot Lists
| Task | Due | Status |
|---|---|---|
| What is RAMMP 4 min â Refilm script/shotlist | Feb 4 | â |
| Day in the Life Owen â Finalize shotlist and script | Feb 4 | â |
| Purdue v2 â Finalize script and shotlist | Feb 6 | â |
| Demo Team Trailer â Finalize and build final shot list | Feb 6 | â |
| The Aging Crisis â Finalize script and shotlist | Feb 6 | â |
| Artist Rendering of Future Vision â Shotlist and script | Feb 6 | â |
Day in the Life â Owen (Prep)
| Task | Due | Status |
|---|---|---|
| Review and finalize Owen outline | Feb 3 | â |
| Schedule filming days with caregivers | Feb 4 | â |
| Prep equipment (camera, audio, lighting) | Feb 5 | â |
| Filming Day 1: Kitchen, workshop, coding | Feb 6 | â |
| Filming Day 2: Gaming, drone flying, Buddy | Feb 7 | â |
| Filming Day 3: Van, outdoor adventure, mountains | Feb 8 | â |
| Backup filming / pickup shots | Feb 9 | â |
đ Week 2: Feb 10 â Feb 16
Day in the Life â Owen (cont.)
| Task | Due | Status |
|---|---|---|
| Filming Day 4: Home navigation, evening routine | Feb 10 | â |
| Filming Day 5: Key interviews (Independence + RAMMP Vision) | Feb 11 | â |
| Capture b-roll: hands, equipment details, textures | Feb 12 | â |
| Begin rough cut assembly | Feb 13-14 | â |
| Review footage, identify gaps | Feb 14 | â |
| Pickup shots if needed | Feb 15 | â |
Pittsburgh Prep
| Task | Due | Status |
|---|---|---|
| Coordinate with Pitt for "What is RAMMP" v2 filming | Feb 10 | â |
| Confirm Pittsburgh schedule and locations | Feb 12 | â |
| Find actress/model for Reflex instructional video | Feb 14 | â |
| Prep Reflex video script and shot list | Feb 15 | â |
| Create MidJourney prompts for vision sequences | Feb 12 | â |
| Generate MidJourney frames | Feb 12-16 | â |
| Create Suno prompts for ambient score | Feb 13 | â |
| Generate Suno music iterations | Feb 13-16 | â |
đ Week 3: Feb 17 â Feb 20
Day in the Life â Owen (Completion)
| Task | Due | Status |
|---|---|---|
| Complete rough cut (5-8 min) | Feb 17-18 | â |
| Add temp music/sound design | Feb 18 | â |
| Internal review | Feb 19 | â |
| Revision pass | Feb 19 | â |
| Export rough cut for stakeholder review | Feb 20 | â |
Pittsburgh Trip Final Prep
| Task | Due | Status |
|---|---|---|
| Organize all vision/MidJourney assets | Feb 17 | â |
| Select best Suno tracks | Feb 18 | â |
| Pack equipment for Pittsburgh trip | Feb 19 | â |
| Confirm all Pittsburgh filming locations | Feb 19 | â |
| Travel to Pittsburgh | Feb 20 | â |
đ¯ Goals
- Finalize scripts and shot lists for all video projects
- Complete Owen's Day in the Life video (filming + rough cut)
- Prepare all assets needed for Pittsburgh filming
âšī¸ Sprint Info
| Focus | Pre-Production + Owen Day in the Life |
| Duration | 18 days |
| Owner | Owen |
| Start | Feb 2 |
| End | Feb 20 |